Boakai Accepts  US$5.7B MIDA -BMMC deal promises 270 megawatts, roads

MONROVIA – Liberia is betting its gold windfall on power and roads. President Joseph Boakai has accepted a US$5.7 billion infrastructure plan tied to Bea Mountain Mining Corporation. The plan promises 270 megawatts, three reservoirs and a national highway corridor. Financing is the real story. Government will set aside extra revenue from higher gold prices instead of borrowing. That spares the debt ledger but ties national ambition to a volatile commodity. It also makes a gold miner central to the country’s power and road future. The five-year timeline runs past the 2029 elections. Lawmakers will receive the agreement after Wednesday’s signing. As THE ANALYST reports, their scrutiny will decide whether this is transformation or another promise.

President Joseph Nyuma Boakai, Sr. has accepted from the Inter-Ministerial Concession Committee (IMCC) a US$5.7 billion (L$1.04 trillion) infrastructure plan that would add 270 megawatts of generating capacity through four new power plants. The plan forms part of an agreement concluded between the Government of Liberia and Bea Mountain Mining Corporation (BMMC), known as the Master Infrastructure Development Agreement (MIDA).

The government described the agreement as “the single most transformative catalyst for the nation’s development in decades.” It said the MIDA is designed to accelerate industrialization and unlock large-scale job creation.

Under the plan, three reservoirs capable of holding a combined 10 billion cubic meters of water would support hydropower generation. Three major transmission lines and grid upgrades would help deliver electricity to homes, hospitals and businesses across Liberia.

According to the government, the agreement marks “a bold new era of economic modernization for the Liberian people” by removing two of the most vexing constraints on the country’s development. It said that by establishing critical infrastructure that strengthens national capacity and attracts global investment, the agreement lays a lasting foundation for Liberia to benefit significantly from emerging investment and trade opportunities based on its rich mineral deposits and strategic location.

Four Plants, 270 Megawatts

The MIDA provides for 270 megawatts of new generating capacity. The plan includes a 100-megawatt hydropower plant on the Via River, two hydropower plants on the St. Paul River with a combined capacity of 110 megawatts, and a 60-megawatt biomass plant.

Hydropower would account for 210 megawatts of the planned capacity. The Via River plant and the SP3 plant on the St. Paul River would each have 100 megawatts of installed capacity. A second plant on the St. Paul River, SP4, would add 10 megawatts.

A 60-megawatt biomass plant near the Via dam would round out the program. The government said it would diversify the electricity sources feeding the grid.

Reservoirs for the Dry Season

To ensure an uninterrupted supply of electricity, the three planned reservoirs would store water for hydropower generation. Reservoirs allow operators to hold water when river flows are higher and release it through turbines when flows fall.

That flexibility can help sustain generation during drier periods, according to the government. It acknowledged, however, that actual output will depend on rainfall, river flows, and how the reservoirs and plants are operated.

Power Lines to Nimba, Bong

The agreement also focuses on getting electricity to the communities that need it. A 150-kilometer main transmission line would connect the power plants to the Mount Coffee substation.

Another 150-kilometer line would link the Via plant to Nimba County, while a 5-kilometer line would serve Bong County. The Nimba and Bong projects each include a substation. The agreement also allocates US$230 million (L$41.94 billion) to reinforce the national grid through upgrades to substations, transformers and transmission infrastructure.

The power plants would generate electricity, the transmission lines would carry it over long distances, and substations and transformers would help move it into the networks that serve customers. More reliable service, the government said, could help hospitals keep essential equipment running and help businesses reduce interruptions to their operations.

Liberia Development Road Corridor

The agreement between the government and BMMC is anchored by the 146-kilometer Liberia Development Road. The flagship highway corridor aims to link the various power plants to key facility centers. This is in addition to US$1 billion (L$182.36 billion) for additional road networks that, according to the government, will crisscross Liberia and connect all regions of the country.

Jobs and the ARREST Agenda

Construction and operation of the projects are expected to create jobs and give Liberians opportunities to develop skills in engineering, construction and power operations. The government said the program advances the ARREST Agenda for Inclusive Development.

It said the program would do so by directing additional mining revenue toward infrastructure that can help farmers reach more buyers, businesses operate more reliably, and communities gain better access to essential services.

Gold Prices to Fund Projects

Describing the arrangement as innovative financing to reduce Liberia’s debt burden, the government said it will set aside additional revenue payable by BMMC, made possible by higher gold prices, to help finance the infrastructure program. BMMC will continue its regular contributions to the Consolidated Account.

The agreement targets implementation over five years. The biomass plant and transmission lines are targeted for completion within two years.

Signing Wednesday, Then Legislature

The IMCC submitted the agreement to the President after months of negotiations. The formal signing is scheduled for Wednesday, November 25, 2026, after which the agreement is to be submitted to the Legislature for consideration.